Other Energy Services

EPCC

Engineering, Procurement, Construction & Commissioning (EPCC) is a particular form of contracting arrangement used in some industries where the EPCC Contractor is made responsible for all the activities from design, procurement, construction, to commissioning and handover of the project to the End-User or Owner. 

PPU 33/11kV AT SABAK BERNAM

Client: Tenaga Nasional Berhad
Location: Selangor, Malaysia
Project Duration: Apr 2018 – Dec 2018
Scope: To install, test, and commission GIS switchgear 33kV and 11kV AIS and ancillary equipment including the construction of temporary PPU PPU style cabin in Sabak Bernam, Selangor Darul Ehsan

PROTECTION UPGRADE FOR SABAH GRID NETWORK UNDER FREQUENCY LOAD SHEDDING

Client: Sabah Electricity Sdn Bhd
Location: Sabah, Malaysia
Project Duration: Jan 2017 – Jul 2018
Scope: Implementation of Protection Upgrade and Associated Works For Whole Sabah Grid Networks – Under Frequency Load Shedding

ABC BENCHMARK PROJECT FOR AREA KOTA MARUDU

Client: Sabah Electricity Sdn Bhd
Location: Sabah, Malaysia
Project Duration: March 2017 – June 2018
Scope: Upgrade AAC cable to ABC under the Task Force Benchmark Project

ABC BENCHMARK PROJECT FOR AREA SEGUNTUR SANDAKAN

Client: Sabah Electricity Sdn Bhd
Location: Sabah, Malaysia
Project Duration: March 2017 – June 2018
Scope: Upgrade AAC cable to ABC under the Task Force Benchmark Project

ABC BENCHMARK PROJECT FOR MERPATI SANDAKAN

Client: Sabah Electricity Sdn Bhd
Location: Sabah, Malaysia
Project Duration: March 2017 – June 2018
Scope: Upgrade AAC cable to ABC under the Task Force Benchmark Project

PPU 33/11kV AT BUKIT RIMAU

Client: Tenaga National Berhad
Location: Selangor, Malaysia
Project Duration: Sept 2017 – Feb 2018
Scope: To install, test, and commission of the Mobile units PPU 33/11kV in Bukit Rimau PPU (Provisional), Shah Alam, Selangor Darul Ehsan

INSTALLATION OF LANTERN HPSV (150W) & LED (90W) FOR LAMPU JALAN KAMPUNG PHASE 8

Client: Tenaga Nasional Berhad
Location: Pahang, Selangor, Johor, Negeri Sembilan & Malacca, Malaysia
Project Duration: Apr 2017 – Jan 2018
Scope: To supply and install village street lights of the Ministry of Rural and Regional Development

Consultancy

Re-evaluation of Consultant’s Recommendation For IPP Project

Client: Powertek Sdn Bhd
Scope: The scope was to re-evaluate the Consultant’s recommendation for the turnkey contract of Powertek IPP project in Malacca.

GSIP Newsprint Plant – Mechanical/Electrical And C&I Consultancy

Client: Genting Sanyen Industrial Paper (GSIP)
Scope: TNEC, in a joint venture with a local consulting firm, provided consultancy services for the mechanical and electrical systems of the newsprint plant. The consultancy services were provided on a lump sum plus reimbursable basis.

Power Plant

Feasibility Study For Sabah IPP

Duration: Aug 1993 – Dec 1993
Client: EPE Power
Scope: TNEC undertook a feasibility study for EPE Power to determine both the financial and technical viability of the proposed IPP Sabah Project.

Kuala Langat Power Plant

Duration: Aug 1993 – Dec 1993
Client: EPE Power
Scope: TNEC undertook a feasibility study for EPE Power to determine both the financial and technical viability of the proposed IPP Sabah Project.

Pakar & Pasir Gudang Combined Cycle

Duration: June 1994 – June 1996
Client: Tenaga Nasional Berhad
Scope: The scope of work involved the procurement, erection, and commissioning of the balance of plant works specifically in the area of plant mechanical and electrical. The plant size was 243 MW respectively.

Kapar Power Station (Phase III)

Client: Tenaga Nasional Berhad
Scope: The scope of work covers the procurement, erection, commissioning, and supervision of the various plant electrical and mechanical auxiliaries, of 2 x 500 MW capacity.

Malacca Combined Cycle Conversion

Duration: Jan 1995 – Nov 1997
Client: Tenaga Nasional Berhad
Scope: This is a turnkey contract undertaken by TNEC is a joint venture with local and international partners. The project involved the Conversion of 2 GE Frame 9 Machines into Combined Cycle operations, of 120 MW capacity.

Relocation Of Gas Turbine From Pasir Gudang To Gelugor

Duration: Feb 1995 – Nov 1995
Client: Tenaga Nasional Berhad
Scope: The scope of work involved the dismantling of one GE Frame 9 (110 MW) at Pasir Gudang Power Station and the transportation to Gelugor Station, reinstallation, and commissioning of the gas turbine. The scope also involved the redesign and construction of the electrical switchgear at Gelugor Power Station.

Relocation Of 2x30MW Gas Turbine From Kapar To Pulau Langkawi

Duration: 5.5 months
Client: Tenaga Nasional Berhad
Scope: The scope of work involved the dismantling of 2 x 30 MW GEC Alsthom GTs at Kapar and the transportation to the Teluk Ewa Power Station in Langkawi, reinstallation, and commissioning of the Gas Turbines. The scope also involved the redesign and construction of the electrical switchgear at Teluk Ewa Power Station in Langkawi.

IPP In Sihanoukville, Cambodia

Duration: 1996 – 1997
Client: Electricite du Combodge, Cambodia
Scope: TNEC participated in the international tender by Asian Development Bank and was the turnkey contractor for the total development of the power plant. The total plant capacity of the diesel power plant is 20 MW.

Ulu Terengganu Hydro Scheme

Duration: 1996
Client: Tenaga Nasional Berhad & Permodalan Terengganu Berhad (PTB)
Scope: The scope of services includes the feasibility study, review and update on the Ulu Terengganu Hydroelectric project.

Extension Of Power House, Supply & Installation Of Diesel Generating Sets

Duration: Jan 1997 0 Dec 1997
Client: Tenaga Nasional Berhad
Scope: This is a fast-track project to increase the installed capacity of TNB’s Pulau Tioman Power Station. The scope of work involved the relocation of 3 nos. of existing 500kW generating sets, new plant-up of 2 x 2.5 MW diesel generating sets, and extension of the existing power house.

Relocation Of The Second Gas Turbine From Kapar To Gelugor

Duration: 1998 – 2000
Client: Tenaga Nasional Berhad
Scope: The scope involved dismantling, relocation of one unit Frame 917E gas Turbine from Sultan Salahuddin Abdul Aziz Shah Power Station, Kapar, Klang to Gelugor Power Station in Penang, reinstallation, and commissioning of the gas turbine.

Kapar Power Station Coal Handling System Refurbishment

Duration: Nov 1998 – May 2000
Client: Tenaga Nasional Berhad
Scope: EPC contract for refurbishment, upgrading and extension works of the coal handling system at Sultan Salahuddin Abdul Aziz Power Station, Kapar, Klang.

Gelugor Power Station Upgrading Project – Construction Of 132kV GIS Substation

Duration: Nov 1999 – Apr 2001
Client: Tenaga Nasional Berhad
Scope: The scope of work involved full turnkey work to design, engineer, manufacture, inspect and test at manufacturer’s place, complete erection, setting to work, and warranty for a period of 12 months after putting into service at the site for a new 132kV GIS Substation.

Gelugor Power Plant Combined Sycle Conversion Project

Duration: Sep 2000 – Dec 2002
Client: Tenaga Nasional Berhad
Scope: The scope of this full turnkey works includes the design, engineering, manufacturing, carrying out quality inspection and testing at work and site, packing for shipment, insurance, delivery to site, erection, testing, and commissioning.

PMU/PPU/SUBSTATIONS

Project Management Services For 275KV Transmission Lines And Substations

Duration: Dec 1993 – Dec 1995
Client: Segari Energy Venture (SEV)
Scope: The scope of services was for Project Management for the Segari Energy Venture 275 kV transmission lines project from SEV Power Station in Lumut to Batu Gajah and 275 kV substations at SEV Power Plant, Air Tawar, and Batu Gajah. Sabah Project.

KLIA Consultancy Services For Package 9 Stage 1

Duration: Apr 1994 – Apr 1995
Client: Kuala Lumpur International Airport Berhad (KLIAB)
Scope: Provision of consultancy services for package 9 (33kV and 11kV distribution network including SCADA). The scope of work includes detailed design, preparation of tender drawings and documents tender evaluation, and tender recommendation reporting to the client.

Electrical Supply System For TNRD’s Testiac Project

Duration: Feb 1994 – May 1995
Client: TNB Research & Development (TNR D)
Scope: EPC’s contract to design, erect and commission the electrical power supply system required for a thermal ice storage project at the Port Dickson Power Station.

KLCC & Danau Desa GIS Substation – Civil & Electrical Package

Duration: 1995 – 1996
Client: Hyusong Industry Co Ltd (HICO)
Scope: The scope of work involved the construction of a 132 kV GIS substation and the supply and erection of 33 kV and 11 kV switchgear for KLCC and Danau Desa GIS substations. The project was completed in mid-1996.

500kV Substations – MV/LV Supply

Duration: Oct 1996 – Dec 1997
Client: MRCB / PNB
Scope: TNEC was awarded the sub-contract Package ST by MRCB/ PNB Consortium to provide turnkey works for the AC Auxiliary Supply to the 500 / 275 kV substations in Junjung, Gurun, Yong Peng (N), and Bukit Batu.

Supply & Erect Of Transmission In TNB System

Duration:
(1) Skudai 132/33 Extension Substation (July 2000)
(2) Kampar 132/33 11kv Substation (July 2000)
(3) Telok Kalong 275kv Substation (July 2000)
(4) Bukit Tengah 132/33kv Extension Substation (Sept 2000)
(5) Pmu 132kv Skudai (Rehab) (Mac 2003
(6) Pmu 275/132kv Bukit Batu Extension (November 2001)
Client: Tenaga Nasional Berhad
Scope: The scope of works covers procurement, supply, delivery, erection, installation, testing, commissioning, and maintenance.

Supply & Erect Of Transmission In TNB System

Duration:
(1) PMU Pasir Gudang 132/ 22kV Substation Extension (June 2000 – Feb 2002)
(2) PMU Tampoi132/22kV Extension (June 2001- January 2002)
(3) PMU Skudai 132/33kV Substation Extension (From June 2000)
(4) PMU Chuping 275kV/132kV Substation Extension (June 2000 – April)
(5) PMU Telok Kalong 275 kV Substation Extension (From June 2000)
(6) PMU Bukit Batu 275/132kV Substation Extension (From June 2000)
(7) PMU Mentakab 132/11kV Extension (From June 2000)
(8) 132kV GIS Extension for Gelugor Substation (From February 2002)
(9) 132kV GIS Extension for Sg. Pinang (From February 2002)
Client: Tenaga Nasional Berhad
Scope: The scope of work involved supply, delivery, installation, testing, commissioning, and maintenance for 12 calendar months from the date of commissioning of Transmission Substation in TNB System.

Remote End Relays Upgrade At Kota Setar & Kuala Perlis Substation (275kV & 132 kV)

Duration: To complete in June 2002
Client: Teknologi Tenaga Perlis Consortium
Scope: The scope of work involved design, supply, installation, testing, and commissioning of the protection and control equipment of 275kV Chuping Feeder I at Kota Setar substation and 132kV Kota Setar – Kuala Perlis Feeders I and II at both ends.

Pergau Power Station Transformer (Stage 2) 275kV/33kV/11kV Temporary Supplies

Duration: From April 2002
Client: Tenaga Nasional Berhad
Scope: The scope of work involved EPC Contract for engineering, procurement and commissioning of the proposed 11kV and 33kV supplies to Pergau Power Station for Stage 2.

Pergau Power Station – Proposed 11kV & 33kV Temporary Supply (Stage 1)

Duration: December 2001 – Jan 2002
Client: Tenaga Nasional Berhad
Scope: The scope of work involved EPC Contract for engineering, procurement, and commissioning of the proposed 11 kV and 33kV supplies to Pergau Power Station and Terang Pumping Station respectively.

Pergau Power Station – Semi-Permanent 275/33/11kV Station Supply (Phase 2)

Duration: July 2002
Client: TNB Hidro Sdn Bhd
Scope: The scope of works consists of the temporary installation of the 275/ 11kV 68MVA Transformer and its associated work and is also inclusive of bridge strengthening, 1SMVA, 33/11kV transformer oil removal, and filling up with nitrogen gas as well as transportation to site.

TTPC – Kota Setar 275kV & 132kV TTPC Relay & Current Transformer Upgrade For Kota Setar/Kuala Perlis Feeder 1 & 2 And Kota Setar/Chuping 275kV

Duration: April 2002
Client: TIPC
Scope: The scope of works cover the procurement, supply, delivery, erection, installation, testing, commissioning and maintenance.

Proposed 275/132kV Line Termination At Bukit Rajah GIS Substation: (1) 132kV Transmission Line CBPS To Bukit Rajah GIS (2) 132kV Transmission Line CBPS To Bukit Rajah & Port Klang To Bukit Rajah GIS

Duration: Feb 2003 – Nov 2003
Client: Tenaga Nasional Berhad
Scope: The scope of works includes supply, erect, string, test, and commissioning of these lines:
- 132kV transmission line CBPS to Bukit Rajah GIS
- 275kV transmission line CBPS to Bukit Rajah GIS and Port Klang to Bukit Rajah GIS
- 132kV transmission line MERU to Bukit Rajah GIS and SHAN to Bukit Rajah GIS

Project – Projek Rangkaian Pembahagian SESB Di Bawah RMK-8

Duration: May 2003
Client: SESB
Scope:
- Construction on a new 33/11 kV PPU, Limbawang, Beaufort
- Construction on a new 33/11 kV PPU, Ranca-Ranca, Labuan
- Construction on a new 33/11 kV PPU, Sandakan
- Construction on a new 33kV Ring System for Tawau Airport from Kalimpang, Tawau.
- Supply, Install, Cabling Works, Test, and
- Commission at PMU Lahad Datu. Timatch-Sabah Parks 11kV ABC Cabling Works

132/33/11kV Sungai Besar & Kuala Selangor Extension

Duration: May 2003
Client: Tenaga Nasional Berhad
Scope: The scope of works include design, manufacture, testing, supply, delivery, installation, com­mission and maintenance for a period of twelve (12) calendar months from the date of commissioning of 132kV, 33kV & 11kV Switchgears and related civil works for PMU Sungai Besar and Kuala Selangor Extensions.

132/11kV Bukit Rambai & Nilai No. 3-2X 1SMVA Transformer Bays

Duration: Marc 2003 – Dec 2003
Client: Tenaga Nasional Berhad
Scope: The scope of works include supply, install, test and commission transformer feeder for transformer 132/11kV MVA at Bukit Rambai Substation and Nilai No.3 Substation.

Grik 275kV/11kV Rehabilitation

Duration: Apr 2003 – Jul 2003
Client: Tenaga Nasional Berhad
Scope: The contract is fast-track in nature and is to be completed on an urgent basis. The scope of works requires TNEC to transfer a 75 MVA transformer, 275 kV current transformer, and two (2) 32.5 MVA reactors from PMU Temenggor to PMU Grik. The substation was successfully commissioned on 25 June 2003.

Others

Feasibility Study For Installation Of Street Lighting Along North – South Highway

Duration: 2 months (early 1997)
Client: Pengurusan Lebuhraya Berhad (PLB)
Scope: TNEC undertook a feasibility study to determine and identify the technical & commercial requirements for the installation of street lighting along the North – South Expressway (NSE).

Development of Data Warehouse For TNB Transmission Network

Duration: Jul 1997 – Nov 1998
Client: Tenaga Nasional Berhad
Scope: A part of a 12-year program to implement and utilize microprocessor­ based technology for local control, protection, recorders, databank, time reference, etc. The 1st phase of the project was intended to utilize the substation control system and databank for a selected few grid substations as a “proof-of-concept” effort.

Relocation Of TNB’s 275kV Overhead Transmission Line Tower & Underground Cable Due To Upgrading Road Works From Alor Gajah To Bandar Melaka

Duration: From July 2002
Client:Tenaga Nasional Berhad
Scope: The scope of work involved design, supply, install, test, and commission of TNB’s 275kV and 132kV Overhead Transmission Line, Tower, and Underground Cable Diversion works due to upgrading road works from Alor Gajah to Bandar Melaka.

Pusat Latihan Gabungan, Pasukan Tempur Tentera Darat, Fasa Di Gemas, N.Sembilan – 11kV Electrical Infrastructure Works

Duration: June 2003
Client: THUB & Kementerian Pertahanan Malaysia
Scope: The scope of work encompasses 11kV Infrastructure Works for a military base in Gemas, Negeri Sembilan under the Ministry of Defense (MINDEF). Works include 11kV cable laying and installation of transformer and ring main unit.

Digital Simulator System

Duration: August 2003
Client: Tenaga Nasional Berhad
Scope: The scope of work encompasses the supply of equipment, fabrication, and engineering work to develop a digital simulator system to train substation operators on SCS systems (Substation Control System)

Relocation Of Transformer 60 MVA And 30 MVA Inclusive Of Termination Works From Transmission & Switchgear

Duration: August 2003
Client: TNB Transmission lpoh, Perak
Scope: Relocation of Transformer 60 MVA and 30 MVA inclusive of termination works from transmission & switchgear.

Relocating OG TNB’s 132kV Underground Cable Due To Upgrading Road Works At Jalan Muar – Melaka – Alor Gajah – Simpang Empat

Duration: Apr 2003 – Aug 2003
Client: Tenaga Nasional Berhad
Scope: The scope of works includes supply, erect, string, test, and commissioning of these lines:
- 132kV transmission line in Kg. Ayer Udang
- 132kV transmission line in Taman Seri Bayu
- 275/132kV transmission line in Kg. Paya Datuk